No | Name of project | Size, Location | Total investment (billion VND) | Investment form | Proposing agency (State/Investor) |
|
| 23 Projects | 71,172 |
|
|
I | INFRASTRUCTURE | 71,127 |
|
| |
A | ROAD BRIDGE | 53,788 |
|
| |
A1 | BRIDGE |
| 14,108 |
|
|
1 | Binh Trieu 2 Bridge and Road (Section 2) | 1. Scale | 6,357 | BOT | TP Technical Infrastructure Investment Joint Stock Company (CII) |
2 | Phu My bridge | Cable-stayed reinforced concrete bridge, length 2100m, MCN 27.5m | 2,914 | BOT | Phu My Construction Investment Joint Stock Company |
3 | Saigon Bridge 2 | - Bridge cross section: 23.5m. | 1,827 | BT | City Technical Infrastructure Investment Joint Stock Company (CII) |
4 | Thu Thiem Bridge 2 | 1,465m long including the path. Connecting Thu Thiem and District 1 | 3,010 | BT | Dai Quang Minh |
A2 | STREET | 39,680 |
|
| |
5 | Expanding Hanoi highway | 1. Scale | 5,322 | BOT | City Technical Infrastructure Investment Joint Stock Company |
6 | Phase 1: Expanding National Highway 1, section An Suong - An Lac | 1. Scale | 4,484 | BOT | IDICO Infrastructure Development Investment Joint Stock Company (IDICO-IDI) |
7 | Construction of 04 main roads in Thu Thiem new urban area | 1. Scale: to build 04 new main traffic routes R1, R2, R3, R4 with a total length of 11.9km, MCN from 11.6m ÷ 55m; build 10 bridges (including 2 viaducts) with a total length of 1.8km. | 8,265 | BT | Dai Quang Minh Real Estate Joint Stock Company |
8 | Technical infrastructure of Northern Residential Area (functional areas No. 3 and No. 4) and completion of North - South trunk road (section from the foot of Thu Thiem bridge 1 to Mai Chi Tho street) in Thu Thiem New Urban Area according to figure Form of Contract BT | 1. Scale: build North-South trunk road with total length of 1,097m, MCN 44.7m; to build internal roads within functional zones No. 3 and No. 4 with a total length of 8,350m, MCN from 18.6-28.6m. | 2,641 | BT | City Technical Infrastructure Investment Joint Stock Company |
9 | Construction of a road connecting to Phu My Bridge | - The East Ring Road is 8,752.24m long, MCN: 67m | 1,440 | BT | Phu My Construction Investment Joint Stock Company |
10 | Road D3 connects to SG - Hiep Phuoc port | The road part is 1,800m long, the MCN has 4 lanes; Rach Rop II bridge is 300m long; Great Canal II bridge is 273m . long | 293 | BT | Investor: DDCity T Co., Ltd. Ngoc Vien Dong urban area |
11 | Road connecting Nguyen Duy Trinh street to Phu Huu industrial park | District 9 | 461 | BOT | Ha Tien 1 Cement Joint Stock Company |
12 | Tan Son Nhat Street - Binh Loi - Outer ring | 1. Scale: length: 13,657km; 40m wide (including 2 branches from Truong Son to Nguyen Thai Son), 60m wide (from Nguyen Thai Son to Go Dua), 30m wide (from Do Dua to Linh Xuan intersection). On the route, there are 03 bridges: Binh Loi, Go Dua, Rach Lang; 06 pedestrian overpasses. | 10,687 | BT | GS Engineering & construction corp |
13 | Public passenger transport by waterway | Route 1 (Bach Dang - Linh Dong) is 10.8km long, 07 berths | 125 | BOO | Investors participating in the selection process: Thuong Nhat Co., Ltd |
14 | Construction of parallel road to the south of HCMC - Long Thanh - Dau Giay expressway (section from An Phu intersection to Ring 2) | Total length of the route is 3,880m, MCN 14-20m including Ba Dat bridge (128.8m long), Muong Kenh bridge (359.1m long) with MCN 14.25m | 869 | BT | Investor: Nam Rach Chiec - Tien Phuoc joint venture |
15 | The connecting section from Pham Van Dong street to Go Dua intersection (NH1) | Line length: 2,750.82m. (the first point connects to Pham Van Dong street, the end point connects to Go Dua intersection (National Highway 1)); MCN 67m (08 lanes for motor vehicles and 06 lanes for mixed traffic); Phase 1: building 02 parallel mixed-vehicle branches. | 2,955 | BT | Investor: Joint Venture HNS VN Investment Joint Stock Company - Van Phu Invest Investment Joint Stock Company - Bac Ai Construction Investment Consulting Joint Stock Company |
16 | Road connecting Vo Van Kiet Street to Ho Chi Minh City - Trung Luong Expressway | - Phase 1 has 04 lanes (14.5m on each side, including: 01 lane for motor vehicles, 01 lane for mixed traffic and sidewalks), the reserve land in the middle is 31m wide. | 2,138 | BOT | Yen Khanh Production, Trade and Service Co., Ltd |
B | WATER SUPPLY - ENVIRONMENT - AQUATIC | 12,469 |
|
| |
17 | Addressing tidal flooding in Ho Chi Minh City area taking into account climate change factors | Building 06 tidal control sluices: Ben Nghe, Tan Thuan, Phu Xuan, Muong Chuoi, Cay Kho, Phu Dinh and building 05 embankment sections at key positions, with elevation lower than tidal peak with a total length of 6,970 square meter | 9,927 | BT | Trung Nam Construction Joint Stock Company |
18 | Tham Luong - Ben Cat canal wastewater treatment plant (Phase 1) | Construction of a wastewater treatment plant with a capacity of: | 2,542 | BT | Phu Dien Trading and Construction Investment Joint Stock Company |
C | US Underground Parking | 2,631 |
|
| |
19 | Underground parking at Le Van Tam park | - Area occupied by surface land: 5,233.1m2; number of underground floors: 04; | 1,748 | BOT | Underground space development investment joint stock company |
20 | Underground parking at Drum Dong stage | - Construction of 07 underground floors + 03 floating floors. | 883 | BOO | Dong Duong Group Co., Ltd |
D | WATERWAY | 1303 |
|
| |
21 | Improvement of Saigon river channel from Ben Suc port (Binh Duong) to Binh Loi bridge | Scale: Dredging the Saigon river channel from Ben Suc port to Binh Loi bridge (71km) + Building a new Binh Loi railway bridge with a length of 1.3km. | 1,303 | BOT | Joint Venture GUD-STD |
E | FACILITIES - URBAN CHANGE | 936 |
|
| |
22 | Construction of internal technical infrastructure in Zone I (Ancient Zone) of Ethnic Culture and History Park, District 9 | - Leveling is about 25,016ha. | 936 | BT | Duc Khai Joint Stock Company |
II | CULTURE - SPORTS | 45 |
|
| |
23 | Building a cinema complex at the Cultural Center of District 12 | - Scale: Including 01 block with 01 ground floor, 02 floors, arranged from 06 to 08 cinema rooms and ancillary items such as lobby, stairs, toilet, office, warehouse; | 45 | BOT | Linh Thanh Tuyen Co., Ltd |